This projectis needed to provide safe and reasonable access and will contribute to the social and economic sustainability of local communities. The reroutes of NFS roads 91 and 178D will be approximately 0.7 miles in length combined.
Location
This project is located along FSR 91, southeast of Hopewell Lake.
Project timeline
1
Scoping Start
03/03/2025
2
Decision
05/2025 (Estimated)
3
Implementation
06/2025 (Estimated)
NEPA / regulatory detail
| Categorical Exclusion | 32.2 (24), 36 Cfr 220.6(E)(24) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | Not Subject to Regulations |
| Project Activity | Road Maintenance; Road Improvements/Construction |
| Forest Service Roads 91 and 178D Reroutes | Decision Signed Date: 05/28/2025 |
| Forests | Carson National Forest |
| Districts | Tres Piedras Ranger District |
| Legal Land Description | Tounship 28N, Range 7E, Section 14 |