The project involves timber stand improvements designed to reduce hazards associated with PG&E's Hat Creek to Westwood transmission line.
Location
Township (T) 35 North (N), Range (R) 40 East (E); T35N, R50E; T34N, R50E; T34N, R60E; T33N, R60E; T33N, R70E; T32N, R70E; T32N, R80E; T31N, R80E; T30N, R90E;and T29N, R90E of the Mount Diablo Meridian
Project timeline
1
Scoping Start
08/22/2019
2
Decision
07/2021 (Estimated)
3
Implementation
09/2021 (Estimated)
NEPA / regulatory detail
| Categorical Exclusion | 32.2 (6), 36 Cfr 220.6(E)(6) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | Not Subject to Regulations |
| Project Activity | Biomass; Fuel Treatments (Non-Activity Fuels); Forest Vegetation Improvements; Timber Sales (Salvage); Timber Sales (Green) |
| Forests | Lassen National Forest |
| Districts | Hat Creek Ranger District; Eagle Lake Ranger District |
| Legal Land Description | Not Applicable |