Stevens Pass Mountain Resort is replacing two long-term "temporary" porta-potties in parking lot #2 with 2 double-vault CXT prefabricated concrete toilets.
Location
North Side of Lot #2 at Stevens Pass Mountain Resort, along Hwy 2 in Stevens Pass, WA.
Project timeline
1
Scoping Start
05/26/2025
2
Decision
07/2025 (Estimated)
3
Implementation
07/2025 (Estimated)
NEPA / regulatory detail
| Categorical Exclusion | 32.2 (22), 36 Cfr 220.6(E)(22) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | Not Subject to Regulations |
| Project Activity | Developed Site Management; Facility Improvements/Construction |
| Stevens Pass Vault Toilet Installation | Decision Signed Date: 07/01/2025 |
| Forests | Mt Baker-Snoqualmie National Forest |
| Districts | Skykomish Ranger District |
| Legal Land Description | Not Applicable |