Decision Memo Completed

West Fork 8th Creek OHV Trail Bridge Replacement

Willamette National Forest Lane, Oregon Middle Fork Ranger District

The purpose of this project is to rebuild the West Fork 8th creek trail bridge. The bridge has failed and collapsed. There is a need for the bridge to be replaced to enhance user safety and protect natural resources.

Location

T20s, R4e, Section 7

Project timeline

1
Scoping Start
06/11/2024
2
Decision
06/2025 (Estimated)
3
Implementation
08/2025 (Estimated)

NEPA / regulatory detail

Categorical Exclusion32.2 (1), 36 Cfr 220.6(E)(1)
Special AuthorityNot Applicable / Other
Notice and Comment RegulationNot Subject to Regulations
Project ActivityTrail Management
West Fork 8th Creek OHV Trail Bridge Replacement Decision MemoDecision Signed Date: 06/03/2025
ForestsWillamette National Forest
DistrictsMiddle Fork Ranger District
Legal Land DescriptionNot Applicable