Build a new Port Chalmers Cabin at a site more easily accessed by users, and decommission the existing site.
Location
The southern end of Port Chalmers on the northwest side of Montague Island at the entrance to Prince William Sound, and 18 Mile of the Copper River Highway.
Project timeline
1
Scoping Start
09/07/2023
2
Comment Period
03/01/2024
3
Objection Period Start
05/10/2024
4
Decision
07/2024 (Estimated)
5
Implementation
04/2025 (Estimated)
NEPA / regulatory detail
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | Not Subject to Regulations |
| Project Activity | Dispersed Recreation Mgmt. |
| Port Chalmers Cabin Relocation | Decision Signed Date: 07/09/2024 |
| Forests | Chugach National Forest |
| Districts | Cordova Ranger District |
| Legal Land Description | Not Applicable |