Forest Service proposal is to continue to provide trail access across Running Creek on the Selway River Trail #4, while protecting the wilderness and fishery resource. Existing bridge could be relocated and replaced, or replaced with a ford.
Location
Selway-Bitterroot Wilderness Running Creek
Project timeline
1
Scoping Start
01/19/2011
2
Comment Period
07/25/2012
3
Decision
02/2013 (Estimated)
4
Implementation
07/2013 (Estimated)
NEPA / regulatory detail
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | 215 |
| Project Activity | Trail Management |
| Access Across Running Creek Project | Decision Signed Date: 12/13/2012 (FS Withdrawn) Legal Notice Date: 12/19/2012 |
| Access Across Running Creek Project - Decision 2 | Decision Signed Date: 02/28/2013 Legal Notice Date: 03/08/2013 |
| Forests | Bitterroot National Forest |
| Districts | West Fork Ranger District |
| Legal Land Description | T30N, R13E, Section PB40 |