Project timeline
1
Scoping Start
09/27/2010
2
Comment Period
04/05/2011
3
Decision
07/2011 (Estimated)
4
Implementation
09/2011 (Estimated)
NEPA / regulatory detail
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | 215 |
| Project Activity | Special Use Authorizations |
| Fred Burr High Lake Dam Access for Repair project 2011 | Decision Signed Date: 07/07/2011 Legal Notice Date: 07/11/2011 |
| Forests | Bitterroot National Forest |
| Districts | Stevensville Ranger District |
| Legal Land Description | Township 7 North, Range 23 West, SW1/4 Section 25, Principle Meridian Montana, Ravalli County |