To create a network of trails from existing single-track trails (2.8 miles), existing trails routes on road beds (4.5 miles), and proposed new single-track construction (8.0 miles).
Location
Lake Como Greater Recreation Area, south side of the Lake.
Project timeline
1
Scoping Start
12/13/2019
2
Decision
02/2020 (Estimated)
3
Implementation
06/2020 (Estimated)
NEPA / regulatory detail
| Categorical Exclusion | 32.12 (4), 36 Cfr 220.6(D)(4); 32.2 (1), 36 Cfr 220.6(E)(1) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | Not Subject to Regulations |
| Project Activity | Trail Management |
| Lake Como South Trails Decision Memo | Decision Signed Date: 02/27/2020 |
| Forests | Bitterroot National Forest |
| Districts | Darby Ranger District |
| Legal Land Description | T 3N, R 21W, Sec 5,6,7 |