The Petrichs would construct a new road crossing a corner of National Forest System (NFS) lands for a distance of 100 feet in length x 50 feet wide to access private property. In exchange the Forest Service would receive administrative access to NF.
Location
Yellowstone Ranger District near Elbow Creek
Project timeline
1
Scoping Start
06/02/2017
2
Decision
05/2018 (Estimated)
3
Implementation
06/2018 (Estimated)
NEPA / regulatory detail
| Categorical Exclusion | 32.12 (7), 36 Cfr 220.6(D)(7); 32.2 (3), 36 Cfr 220.6(E)(3) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | Not Subject to Regulations |
| Project Activity | Land Use Adjustments; Special Use Authorizations |
| Petrich Access Road | Decision Signed Date: 05/31/2018 |
| Forests | Custer Gallatin National Forest |
| Districts | Yellowstone Ranger District |