Environmental Assessment Completed

Sibanye Stillwater Mining Company's East Boulder Mine Stage 6 Tailings Storage Facility Amendment

Custer Gallatin National Forest Sweet Grass, Montana Yellowstone Ranger District

SSMC East Boulder Mine proposes expanding the existing TSF an additional 14 ft. elevation using the same construction and operation methods as approved in stages 1 to 5. Final crest elevation is designed at 6,344 feet.

Location

East Boulder Mine (EBM), Sweet Grass County, approx.. 16 miles south of McCloud, MT in the East Boulder drainage. Access is by State Route #298 and Forest Service Road #205.

Project timeline

1
Scoping Start
11/08/2018
2
Comment Period
05/15/2020
3
Objection Period Start
09/11/2020
4
Decision
11/2020 (Estimated)
5
Implementation
11/2020 (Estimated)

NEPA / regulatory detail

Special AuthorityNot Applicable / Other
Notice and Comment Regulation218 (2013) Non-HFRA
Project ActivityMinerals Or Geology Plans Of Operations
Sibanye Stillwater Mining Company's East Boulder Mine Stage 6 Tailings Storage Facility AmendmentDecision Signed Date: 11/02/2020
ForestsCuster Gallatin National Forest
DistrictsYellowstone Ranger District
Legal Land DescriptionTownship 4 South, Range 13 East, Sections 2 and 11, Principal Meridian.
Minerals and geology