The East Rosebud Road #2177 was damage in 2022 flood event. Summer '23 road was repaired and section of temp constructed. This project will improve the temporary road to a permanent road, and replace the temporary bridge with a permanent bridge.
Location
East Rosebud Road #2177 Mile 4.6-9.96
Project timeline
1
Scoping Start
03/25/2024
2
Decision
08/2024 (Estimated)
3
Implementation
08/2024 (Estimated)
NEPA / regulatory detail
| Categorical Exclusion | 32.2 (18), 36 Cfr 220.6(E)(18); 32.2 (24), 36 Cfr 220.6(E)(24) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | Not Subject to Regulations |
| Project Activity | Road Maintenance; Road Improvements/Construction |
| East Rosebud Road Reconstruction | Decision Signed Date: 08/05/2024 |
| Forests | Custer Gallatin National Forest |
| Districts | Beartooth Ranger District |
| Legal Land Description | T. 6S;R.17E Sec 21,16,15,10,11 |