The proposal is to restore the flow of Armstrong to its pre-flood channel with a diversion installation.
Location
1600 feet of pre-flood channel of armstrong creek above confluence with E rosebud lake.
Project timeline
1
Scoping Start
03/25/2024
2
Decision
08/2024 (Estimated)
3
Implementation
08/2024 (Estimated)
NEPA / regulatory detail
| Categorical Exclusion | 32.2 (18), 36 Cfr 220.6(E)(18) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | Not Subject to Regulations |
| Project Activity | Watershed Improvements |
| Armstrong Creek Restoration Decision Memo | Decision Signed Date: 08/07/2024 |
| Forests | Custer Gallatin National Forest |
| Districts | Beartooth Ranger District |
| Legal Land Description | Not Applicable |