Sequel Energy proposes to construct a well pad, access approach, and install utilities along the access approach within the developed North Branch Oil Field.
Location
22 miles southwest of Watford City, ND
Project timeline
1
Scoping Start
09/19/2011
2
Comment Period
05/07/2012
3
Decision
06/2012 (Estimated)
4
Implementation
07/2012 (Estimated)
NEPA / regulatory detail
| Categorical Exclusion | 32.2 (3), 36 Cfr 220.6(E)(3) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | 215 |
| Project Activity | Natural Gas; Oil |
| Sequel Energy, LLC North Branch 44-35 Oil & Gas Well | Decision Signed Date: 06/11/2012 Legal Notice Date: 06/14/2012 |
| Forests | Dakota Prairie Grasslands |
| Districts | Mckenzie Ranger District |
| Legal Land Description | SESE Section 35, T.148N., R.102W., 5th PM, McKenzie County, North Dakota. |