True Oil, LLC proposes to construct a well pad, access approach, and install utilities along the access approach within the developed Red Wing Creek Oil Field.
Location
Located 19 air miles southwest of Watford City, ND.
Project timeline
1
Scoping Start
11/18/2010
2
Comment Period
05/21/2012
3
Decision
08/2012 (Estimated)
4
Implementation
08/2012 (Estimated)
NEPA / regulatory detail
| Categorical Exclusion | 32.3 (3) |
| Special Authority | Oil & Gas - Sec. 390, Energy Policy Act Of 2005 (Sec 390) |
| Notice and Comment Regulation | 215 |
| Project Activity | Special Use Authorizations; Natural Gas; Oil |
| True Oil, LLC True Federal 31-32 | Decision Signed Date: 08/02/2012 Legal Notice Date: 08/06/2012 |
| Forests | Dakota Prairie Grasslands |
| Districts | Mckenzie Ranger District |
| Legal Land Description | NWNE Section 32, T148N, R101W |