Burying a 10-inch poly pipeline along an existing pipeline corridor in Section 15, T.148N., R.98W., 5th PM, McKenzie County, North Dakota.
Location
10 air miles SE of Watford City, ND.
Project timeline
1
Scoping Start
08/06/2012
2
Comment Period
08/06/2012
3
Decision
10/2012 (Estimated)
4
Implementation
11/2012 (Estimated)
NEPA / regulatory detail
| Categorical Exclusion | 32.3 (3) |
| Special Authority | Oil & Gas - Sec. 390, Energy Policy Act Of 2005 (Sec 390) |
| Notice and Comment Regulation | 215 |
| Project Activity | Natural Gas |
| Hiland Operating, L.L.C. Natural Gas Gathering Pipeline | Decision Signed Date: 10/17/2012 Legal Notice Date: 10/20/2012 |
| Forests | Dakota Prairie Grasslands |
| Districts | Mckenzie Ranger District |
| Legal Land Description | Section 15, T.148N., R.98W., 5th PM, McKenzie County, North Dakota. |