Upgrade an existing 69kV transmission line to 115kV. Replacement of the poles and wires. All construction would take place within the existing 50 foot wide ROW.
Location
Sections 2, 3, 9, 10, T147N, R103W; Sections 3, 19, 30, and 31, T148N, R102W; and Section 35, T148N, R103W, 5th PM, McKenzie County, North Dakota.
Project timeline
1
Scoping Start
08/30/2012
2
Comment Period
08/30/2012
3
Decision
06/2013 (Estimated)
4
Implementation
08/2013 (Estimated)
NEPA / regulatory detail
| Categorical Exclusion | 32.2 (2), 36 Cfr 220.6(E)(2) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | 215 |
| Project Activity | Special Use Authorizations |
| McKenzie Electric Coop, Inc. Transmission Power Line Upgrade(Hay Butte to G | Decision Signed Date: 06/06/2013 Legal Notice Date: 06/11/2013 |
| Forests | Dakota Prairie Grasslands |