Decision Memo Completed

Basin Electric Power Cooperative Gap Substation Expansion

Dakota Prairie Grasslands McKenzie, North Dakota Mckenzie Ranger District

The project consists of constructing two 17.4 MVAR capacitor banks on a roughly rectangular parcel immediately adjacent to the existing Gap Substation. The area permitted for the substation addition is approximately 4.40 acres.

Location

Section 20, T147N, R103W, 5th PM, McKenzie County, North Dakota

Project timeline

1
Scoping Start
08/14/2012
2
Decision
07/2014 (Estimated)
3
Implementation
10/2014 (Estimated)

NEPA / regulatory detail

Categorical Exclusion32.2 (3), 36 Cfr 220.6(E)(3)
Special AuthorityNot Applicable / Other
Notice and Comment RegulationNot Subject to Regulations
Project ActivitySpecial Use Authorizations
Basin Electric Power Cooperative Gap Substation ExpansionDecision Signed Date: 07/08/2014
ForestsDakota Prairie Grasslands
DistrictsMckenzie Ranger District
Legal Land DescriptionNot Applicable
Special use management