upgrade 7863 feet of overhead and install 614 feet of buried three phase electric line to connect Continental 1X-21H and 1-25H oil wells on private land
Location
28 miles north of Belfield, ND
Project timeline
1
Scoping Start
01/29/2013
2
Comment Period
01/30/2013
3
Decision
07/2013 (Estimated)
4
Implementation
10/2013 (Estimated)
NEPA / regulatory detail
| Categorical Exclusion | 32.2 (3), 36 Cfr 220.6(E)(3) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | 215 |
| Project Activity | Special Use Authorizations |
| Roughrider Electric upgrade/intall overhead & Buried Electric Line | Decision Signed Date: 07/11/2013 Legal Notice Date: 07/11/2013 |
| Forests | Dakota Prairie Grasslands |
| Districts | Medora Ranger District |
| Legal Land Description | 28-144-99 |