Proposal to replace deteriorating steel line with approximately 3800 ft. of new 3 inch high pressure fiberglass pipe.
Location
Approximately 13 air miles NE of Medora, ND
Project timeline
1
Scoping Start
08/14/2013
2
Decision
09/2013 (Estimated)
3
Implementation
10/2013 (Estimated)
NEPA / regulatory detail
| Categorical Exclusion | 32.2 (3), 36 Cfr 220.6(E)(3) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | Not Subject to Regulations |
| Project Activity | Minerals Or Geology Plans Of Operations |
| Whiting BSMU 2501 Water Injection Line | Decision Signed Date: 09/27/2013 |
| Forests | Dakota Prairie Grasslands |
| Districts | Medora Ranger District |
| Legal Land Description | E 1/2 Section 25, T142N, R101W, Billings County |