Proposal to extend existing flowline 2,600 ft. within same trench as BSMU 3001 line replacement project. New extension would be new 3" high pressure fiberglass line.
Location
Located approximately 13 air miles NE of Medora, ND
Project timeline
1
Scoping Start
08/14/2013
2
Decision
07/2014 (Estimated)
3
Implementation
10/2014 (Estimated)
NEPA / regulatory detail
| Categorical Exclusion | 32.2 (3), 36 Cfr 220.6(E)(3) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | Not Subject to Regulations |
| Project Activity | Minerals Or Geology Plans Of Operations |
| BSMU 3006 Flowline | Decision Signed Date: 07/01/2014 |
| Forests | Dakota Prairie Grasslands |
| Districts | Medora Ranger District |
| Legal Land Description | wW 1/2 Section 30, T142N, R100W |