Environmental Assessment Completed

International Western Company water pumping facility and associated utilities

Dakota Prairie Grasslands McKenzie, North Dakota Dakota Prairie Grasslands All Units

The purpose for this facility is to distribute water for oil field exploration and development. Disturbance would be about 10.2 acres during construction but be about 0.3 acres for operation and maintenance following interim reclamation.

Location

Sections 6, 7, and 18, T.153N., R.94W., Sections 1 and 12, T.153N., R.95W., and Section 31, T.154N., R.95W., all within the 5th PM, McKenzie Co, North Dakota.

Project timeline

1
Scoping Start
05/30/2014
2
Comment Period
05/30/2014
3
Decision
11/2015 (Estimated)
4
Implementation
12/2014 (Estimated)

NEPA / regulatory detail

Special AuthorityNot Applicable / Other
Notice and Comment Regulation218 (2013) Non-HFRA
Project ActivitySpecial Use Authorizations
Charlson Industrial Water Supply-Intake FacilitiesDecision Signed Date: 11/03/2014
Charlson Industrial Water Supply Pipeline RouteDecision Signed Date: 11/19/2015
ForestsDakota Prairie Grasslands
DistrictsMckenzie Ranger District
Legal Land DescriptionNot Applicable
Special use management