The purpose for this facility is to distribute water for oil field exploration and development. Disturbance would be about 10.2 acres during construction but be about 0.3 acres for operation and maintenance following interim reclamation.
Location
Sections 6, 7, and 18, T.153N., R.94W., Sections 1 and 12, T.153N., R.95W., and Section 31, T.154N., R.95W., all within the 5th PM, McKenzie Co, North Dakota.
Project timeline
1
Scoping Start
05/30/2014
2
Comment Period
05/30/2014
3
Decision
11/2015 (Estimated)
4
Implementation
12/2014 (Estimated)
NEPA / regulatory detail
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | 218 (2013) Non-HFRA |
| Project Activity | Special Use Authorizations |
| Charlson Industrial Water Supply-Intake Facilities | Decision Signed Date: 11/03/2014 |
| Charlson Industrial Water Supply Pipeline Route | Decision Signed Date: 11/19/2015 |
| Forests | Dakota Prairie Grasslands |
| Districts | Mckenzie Ranger District |
| Legal Land Description | Not Applicable |