The proposal includes access roads, underground electric and fiber optic lines, and saltwater, oil, fresh water, and gas pipelines, and any utilities or pipelines that may be necessary for production.
Location
Approximately 20 southwest of Watford City, ND
Project timeline
1
Scoping Start
07/05/2014
2
Comment Period
07/08/2014
3
Decision
08/2015 (Estimated)
4
Implementation
08/2015 (Estimated)
NEPA / regulatory detail
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | 218 (2013) Non-HFRA |
| Project Activity | Minerals Or Geology Plans Of Operations |
| True Federal 11-1 1-6H, 11-4 4-9H, 13-31 31-32H, 14-30 30-29H, 43-42 and... | Decision Signed Date: 08/18/2015 |
| Forests | Dakota Prairie Grasslands |
| Districts | Mckenzie Ranger District |
| Legal Land Description | T.147N., R.101W., and T.148N., R.101W., 5th Principal Meridian, McKenzie County, North Dakota. |