200 feet of access road to existing Medora Substation
Location
Approximately 6 air miles SW of Medora, ND
Project timeline
1
Scoping Start
08/15/2014
2
Decision
10/2014 (Estimated)
3
Implementation
11/2014 (Estimated)
NEPA / regulatory detail
| Categorical Exclusion | 32.2 (3), 36 Cfr 220.6(E)(3) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | Not Subject to Regulations |
| Project Activity | Special Use Authorizations |
| Upper Missouri G&T Cooperative Access Road | Decision Signed Date: 10/10/2014 |
| Forests | Dakota Prairie Grasslands |
| Districts | Medora Ranger District |
| Legal Land Description | Section 14, T139N, R102W |