Environmental Assessment Completed

East Yellowstone Trail NFSR 7901 Road Improvements

Dakota Prairie Grasslands Slope, North Dakota Medora Ranger District

This project proposes improvements to National Forest System Road 7901, also known as the East Yellowstone Trail. Improvements include grading and some horizontal and vertical realignment. The project would also increase the easement to Slope County.

Location

The project is located within Slope County, North Dakota four miles northeast of Rhame.

Project timeline

1
Scoping Start
04/10/2015
2
Comment Period
06/30/2015
3
Decision
08/2015 (Estimated)
4
Implementation
09/2015 (Estimated)

NEPA / regulatory detail

Special AuthorityNot Applicable / Other
Notice and Comment Regulation218 (2013) Non-HFRA
Project ActivityRoad Maintenance; Road Improvements/Construction
East Yellowstone Trail NFSR 7901 Road Improvements ProjectDecision Signed Date: 08/13/2015
ForestsDakota Prairie Grasslands
DistrictsMedora Ranger District
Legal Land DescriptionTownship 133 North, Range 102 West, Sections 20, 29, and 30, and T133N, R103W, Sections 28 and 33.
Road management