The DPG has begun a process to realign its LRMP with the 2012 Final Planning Rule (see: 36 Code of Federal Regulations 219). In particular, the DPG will address the purpose of the monitoring plan program set forth in 36 CFR 219.12(a)(1).
Location
Dakota Prairie Grasslands
Project timeline
1
Scoping Start
05/10/2016
2
Comment Period
05/10/2016
3
Decision
08/2016 (Estimated)
4
Implementation
08/2016 (Estimated)
NEPA / regulatory detail
| Categorical Exclusion | 32.2 (16), 36 Cfr 220.6(E)(16) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | 219 (2012) |
| Project Activity | Plan Amendment |
| Dakota Prairie Grasslands Monitoring Plan Transition | Decision Signed Date: 08/09/2016 |
| Forests | Dakota Prairie Grasslands |
| Districts | Dakota Prairie Grasslands All Units |
| Legal Land Description | Not Applicable |