Master Development plan would authorize agencies to approve ten well pad expansions or new pads and authorize 54 wells to facilitate development of federal and private minerals for Petro-Hunt, Continental Resources and Slawson Exploration Company.
Location
Northeastern McKenzie County
Project timeline
1
Scoping Start
04/28/2016
2
Comment Period
04/28/2016
3
Objection Period Start
04/27/2018
4
Decision
06/2018 (Estimated)
5
Implementation
08/2018 (Estimated)
NEPA / regulatory detail
| Special Authority | Oil & Gas - Sec. 390, Energy Policy Act Of 2005 (Sec 390); Forest Service Energy Implementation Plan |
| Notice and Comment Regulation | 218 (2013) Non-HFRA |
| Project Activity | Minerals Or Geology Plans Of Operations |
| Antelope Master Development Plan | Decision Signed Date: 06/25/2018 |
| Forests | Dakota Prairie Grasslands |
| Districts | Mckenzie Ranger District |
| Legal Land Description | T. 153N, R. 93W, Sections 31-32, T. 153N, R. 94W, Sections 10, 14-15 and T. 153N, R. 95W, Section 11 |