Environmental Assessment Completed

Antelope Master Development Plan

Dakota Prairie Grasslands McKenzie, North Dakota Dakota Prairie Grasslands All Units

Master Development plan would authorize agencies to approve ten well pad expansions or new pads and authorize 54 wells to facilitate development of federal and private minerals for Petro-Hunt, Continental Resources and Slawson Exploration Company.

Location

Northeastern McKenzie County

Project timeline

1
Scoping Start
04/28/2016
2
Comment Period
04/28/2016
3
Objection Period Start
04/27/2018
4
Decision
06/2018 (Estimated)
5
Implementation
08/2018 (Estimated)

NEPA / regulatory detail

Special AuthorityOil & Gas - Sec. 390, Energy Policy Act Of 2005 (Sec 390); Forest Service Energy Implementation Plan
Notice and Comment Regulation218 (2013) Non-HFRA
Project ActivityMinerals Or Geology Plans Of Operations
Antelope Master Development PlanDecision Signed Date: 06/25/2018
ForestsDakota Prairie Grasslands
DistrictsMckenzie Ranger District
Legal Land DescriptionT. 153N, R. 93W, Sections 31-32, T. 153N, R. 94W, Sections 10, 14-15 and T. 153N, R. 95W, Section 11
Minerals and geology