McKenzie Electric Cooperative, Inc. proposes to install approximately 5433 feet of three-phase, buried electric cable with associated above ground structures along NFSRs 883-1 and 885 to service Silurian's 9-1 and 18-1 locations.
Location
T153N, R95W, Section 10, 5th PM along NFSRs 883-1 and 885
Project timeline
1
Scoping Start
10/04/2017
2
Decision
12/2017 (Estimated)
3
Implementation
03/2018 (Estimated)
NEPA / regulatory detail
| Categorical Exclusion | 32.2 (3), 36 Cfr 220.6(E)(3) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | Not Subject to Regulations |
| Project Activity | Special Use Authorizations |
| McKenzie Electric Cooperative, Inc. Silurian 9-1 and 18-1 Electrical System | Decision Signed Date: 12/17/2017 |
| Forests | Dakota Prairie Grasslands |
| Districts | Mckenzie Ranger District |
| Legal Land Description | T153N, R95W, Section 10, 5th PM |