Decision Memo Completed

McKenzie Electric Cooperative, Inc. Silurian 9-1 and 18-1 Electrical System

Dakota Prairie Grasslands McKenzie, North Dakota Dakota Prairie Grasslands All Units

McKenzie Electric Cooperative, Inc. proposes to install approximately 5433 feet of three-phase, buried electric cable with associated above ground structures along NFSRs 883-1 and 885 to service Silurian's 9-1 and 18-1 locations.

Location

T153N, R95W, Section 10, 5th PM along NFSRs 883-1 and 885

Project timeline

1
Scoping Start
10/04/2017
2
Decision
12/2017 (Estimated)
3
Implementation
03/2018 (Estimated)

NEPA / regulatory detail

Categorical Exclusion32.2 (3), 36 Cfr 220.6(E)(3)
Special AuthorityNot Applicable / Other
Notice and Comment RegulationNot Subject to Regulations
Project ActivitySpecial Use Authorizations
McKenzie Electric Cooperative, Inc. Silurian 9-1 and 18-1 Electrical SystemDecision Signed Date: 12/17/2017
ForestsDakota Prairie Grasslands
DistrictsMckenzie Ranger District
Legal Land DescriptionT153N, R95W, Section 10, 5th PM
Special use management