The project proposes to apply an adaptive management strategy using a variety of tools to effectively manage and restore rangelands managed by the District in accordance with land management plan direction.
Location
Grand River Ranger District
Project timeline
1
Scoping Start
07/13/2018
2
Comment Period
09/12/2020
3
Objection Period Start
09/23/2022
4
Decision
11/2022 (Estimated)
5
Implementation
02/2023 (Estimated)
NEPA / regulatory detail
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | 218 (2013) Non-HFRA |
| Project Activity | Rangeland Vegetation Improvements |
| Grand River and Cedar River Adaptive Management Plan | Decision Signed Date: 11/22/2022 |
| Forests | Dakota Prairie Grasslands |
| Districts | Grand River Ranger District |
| Legal Land Description | Not Applicable |