The Goodnight Midstream Midway to Cleetwood Pipeline Project would consist of installing 0.77 miles (4,050 feet) of 8-inch Star Fiberglass pipeline within a 20-foot right-of-way (4.6 acres) and will be buried to a depth of 60 inches on NFS lands.
Location
Section 27, Township 152N, Range 97W, 5th PM, McKenzie County, North Dakota
Project timeline
1
Scoping Start
10/14/2021
2
Decision
11/2021 (Estimated)
3
Implementation
11/2021 (Estimated)
NEPA / regulatory detail
| Categorical Exclusion | 32.2 (3), 36 Cfr 220.6(E)(3) |
| Special Authority | Oil & Gas - Sec. 390, Energy Policy Act Of 2005 (Sec 390) |
| Notice and Comment Regulation | Not Subject to Regulations |
| Project Activity | Special Use Authorizations |
| Goodnight Midstream Midway to Cleetwood Pipeline Project | Decision Signed Date: 11/17/2021 |
| Forests | Dakota Prairie Grasslands |
| Districts | Mckenzie Ranger District |
| Legal Land Description | Not Applicable |