Decision Memo Completed

Cobra Oil & Gas North Branch Saltwater Pipeline

Dakota Prairie Grasslands McKenzie, North Dakota Mckenzie Ranger District

Cobra Oil and Gas proposes to construct a saltwater pipeline across National Forest System lands in McKenzie County, North Dakota.

Location

Section 35, T148N, R102W, 5th PM, McKenzie County, North Dakota

Project timeline

1
Scoping Start
05/20/2022
2
Decision
07/2022 (Estimated)
3
Implementation
08/2022 (Estimated)

NEPA / regulatory detail

Categorical Exclusion32.2 (3), 36 Cfr 220.6(E)(3)
Special AuthorityNot Applicable / Other
Notice and Comment RegulationNot Subject to Regulations
Project ActivityMinerals Or Geology Plans Of Operations
Cobra Oil & Gas North Branch Saltwater PipelineDecision Signed Date: 07/27/2022
ForestsDakota Prairie Grasslands
DistrictsMckenzie Ranger District
Legal Land DescriptionSection 35, T148N, R102W, 5th PM, McKenzie County, North Dakota
Minerals and geology