Maintenance and reroute of portion of the Maah Daah Hey Trail including 23,000 feet of trail restoration and 1,200 feet of trail realignment
Location
2, 3, 10, 15 T145N R100W; 2, 3, 11, 13, 14, 24, 25 T146N R100W; 22, 27, 34 T147N R100W; 11 T146N R100W; 13 T146N R100W
Project timeline
1
Scoping Start
06/17/2022
2
Decision
09/2022 (Estimated)
3
Implementation
09/2022 (Estimated)
NEPA / regulatory detail
| Categorical Exclusion | 32.12 (4), 36 Cfr 220.6(D)(4); 32.2 (1), 36 Cfr 220.6(E)(1) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | Not Subject to Regulations |
| Project Activity | Trail Management |
| Maah Daah Hey Trail North | Decision Signed Date: 09/02/2022 |
| Forests | Dakota Prairie Grasslands |
| Districts | Mckenzie Ranger District |
| Legal Land Description | Not Applicable |