Eight pipelines, ten stock tanks, and one well
Location
Sections 3, 5, 6, 7, 8 T140N R103W; Section 31 T141N R102W
Project timeline
1
Scoping Start
03/21/2022
2
Decision
11/2022 (Estimated)
3
Implementation
11/2022 (Estimated)
NEPA / regulatory detail
| Categorical Exclusion | 32.2 (9), 36 Cfr 220.6(E)(9) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | Not Subject to Regulations |
| Project Activity | Grazing Structural Improvements |
| Allotment 166 Range Water System | Decision Signed Date: 11/21/2022 |
| Forests | Dakota Prairie Grasslands |
| Districts | Medora Ranger District |
| Legal Land Description | Not Applicable |