One pipeline and two stock tanks
Location
Section 13, T139N R101W
Project timeline
1
Scoping Start
03/21/2022
2
Decision
11/2022 (Estimated)
3
Implementation
11/2022 (Estimated)
NEPA / regulatory detail
| Categorical Exclusion | 32.2 (9), 36 Cfr 220.6(E)(9) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | Not Subject to Regulations |
| Project Activity | Grazing Structural Improvements |
| Forests | Dakota Prairie Grasslands |
| Districts | Medora Ranger District |
| Legal Land Description | Not Applicable |