Construction of approximately 2059 feet of road east of existing road and removal of approximately 2000 feet of the existing road to reduce impacts to wetlands and reduce issue with water overtopping the road.
Location
Sections 3 and 10, T135N R106W
Project timeline
1
Scoping Start
06/15/2023
2
Decision
12/2023 (Estimated)
3
Implementation
12/2023 (Estimated)
NEPA / regulatory detail
| Categorical Exclusion | 32.2 (24), 36 Cfr 220.6(E)(24) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | Not Subject to Regulations |
| Project Activity | Road Improvements/Construction |
| NFSR 779 Realignment | Decision Signed Date: 12/06/2023 |
| Forests | Dakota Prairie Grasslands |
| Districts | Medora Ranger District |
| Legal Land Description | Not Applicable |