North Dakota State Water Commission Southwest Water Pipeline Project to increase delivery of potable water to the West Zone Service Area by construction of four ten-inch diameter pipelines to parallel NDDWR SWPP existing main transmission line
Location
Secs. 33,34 T140N R100W; Secs. 5,6,8,9,12 T139N R101W; Secs. 20,21,29 T140N R103W
Project timeline
1
Scoping Start
07/10/2024
2
Decision
09/2024 (Estimated)
3
Implementation
05/2025 (Estimated)
NEPA / regulatory detail
| Categorical Exclusion | 32.2 (3), 36 Cfr 220.6(E)(3) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | Not Subject to Regulations |
| Project Activity | Special Use Authorizations |
| Southwest Water Pipeline Project | Decision Signed Date: 09/18/2024 |
| Forests | Dakota Prairie Grasslands |
| Districts | Medora Ranger District |
| Legal Land Description | Not Applicable |