Decision Memo Completed

Allotment 204 Water System

Dakota Prairie Grasslands Billings, North Dakota Medora Ranger District

Water pipeline re-route and stock tank installation.

Location

Sects 17, 18, 19, T138N, R100W

Project timeline

1
Scoping Start
09/24/2024
2
Decision
10/2024 (Estimated)
3
Implementation
04/2025 (Estimated)

NEPA / regulatory detail

Categorical Exclusion32.2 (9), 36 Cfr 220.6(E)(9)
Special AuthorityNot Applicable / Other
Notice and Comment RegulationNot Subject to Regulations
Project ActivityGrazing Allotment Management; Grazing Structural Improvements
Allotment 204 Water SystemDecision Signed Date: 10/08/2024
ForestsDakota Prairie Grasslands
DistrictsMedora Ranger District
Legal Land DescriptionNot Applicable
Grazing management