Decision Memo Completed

Intermountain Infrastructure Group, LLC Fiber Optic Installation

Dakota Prairie Grasslands Slope, North Dakota Medora Ranger District

Installation of approximately 3,000 feet of fiber optic cable on National Forest System (NFS) land, within an existing ROW.

Location

North Dakota Highway 12, 5 miles west of Marmarth, ND

Project timeline

1
Scoping Start
03/13/2025
2
Decision
05/2025 (Estimated)
3
Implementation
06/2025 (Estimated)

NEPA / regulatory detail

Categorical Exclusion32.2 (2), 36 Cfr 220.6(E)(2)
Special AuthorityNot Applicable / Other
Notice and Comment RegulationNot Subject to Regulations
Project ActivitySpecial Use Authorizations
Intermountain Infrastructure Group, LLC Fiber Optic InstallationDecision Signed Date: 05/16/2025
ForestsDakota Prairie Grasslands
DistrictsMedora Ranger District
Legal Land DescriptionSection 30, T133N, R106W
Special use management