MEC has requested to bury 660 feet of new power line across National Forest System lands to private property located in Township 21 North, Range 17 West in Section 4.
Location
T21N, R17W, Section 4; Approximately 6 miles north of Condon.
Project timeline
1
Scoping Start
02/03/2016
2
Decision
03/2016 (Estimated)
3
Implementation
06/2016 (Estimated)
NEPA / regulatory detail
| Categorical Exclusion | 32.2 (2), 36 Cfr 220.6(E)(2) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | Not Subject to Regulations |
| Project Activity | Special Use Authorizations |
| Missoula Electric Coop Line Burial Project (T21N, R17W, Section 4) | Decision Signed Date: 03/21/2016 |
| Forests | Flathead National Forest |
| Districts | Swan Lake Ranger District |
| Legal Land Description | Not Applicable |