Replacing an underground powerline (300 feet) to a BNSF railroad signal.
Location
Nyack Flats
Project timeline
1
Scoping Start
07/31/2019
2
Decision
10/2019 (Estimated)
3
Implementation
10/2019 (Estimated)
NEPA / regulatory detail
| Categorical Exclusion | 32.2 (3), 36 Cfr 220.6(E)(3) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | Not Subject to Regulations |
| Project Activity | Special Use Authorizations |
| Flathead Electric Line Replacement Nyack Flats | Decision Signed Date: 10/09/2019 |
| Forests | Flathead National Forest |
| Districts | Hungry Horse Ranger District |
| Legal Land Description | Not Applicable |