Decision Memo Completed

Adkins Lincoln Electric Line Install

Flathead National Forest Flathead, Montana Tally Lake Ranger District

Lincoln Electric Company is requesting to bury 6,000 feet of new power line across National Forest System lands to service private lands.

Location

Power line will extend from an existing location on Good Creek Road along NFSR 2873.

Project timeline

1
Scoping Start
04/14/2021
2
Decision
05/2021 (Estimated)
3
Implementation
05/2021 (Estimated)

NEPA / regulatory detail

Categorical Exclusion32.2 (2), 36 Cfr 220.6(E)(2)
Special AuthorityNot Applicable / Other
Notice and Comment RegulationNot Subject to Regulations
Project ActivitySpecial Use Authorizations
Adkins Lincoln Electric Line InstallDecision Signed Date: 05/03/2021
ForestsFlathead National Forest
DistrictsTally Lake Ranger District
Legal Land DescriptionNE4,NW4,Section 23, T32N, R24W and NE4, Section 22, T32N, R24W