The Forest Service is considering a proposal from LEC to install 6,637 feet of electric line to private land.
Location
Power line would extend from NFSR 2929, Hill Meadow Road, along NFSR 11206, Upper Nineteen Road, to private property.
Project timeline
1
Scoping Start
04/14/2021
2
Decision
10/2021 (Estimated)
3
Implementation
10/2021 (Estimated)
NEPA / regulatory detail
| Categorical Exclusion | 32.2 (2), 36 Cfr 220.6(E)(2) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | Not Subject to Regulations |
| Project Activity | Special Use Authorizations |
| Chang Lincoln Electric Line Install | Decision Signed Date: 10/18/2021 |
| Forests | Flathead National Forest |
| Districts | Tally Lake Ranger District |
| Legal Land Description | NE 1/4 NE 1/4, E 1/2 NW 1/4 Sec 19, T31N, R23W |