Decision Memo Completed

InterBel Fiber Optic Cable Install

Flathead National Forest Flathead, Montana Tally Lake Ranger District

Extend InterBel's existing transport network to a new interconnect point north of Kalispell and ensure continued reliability of telecommunications and broadband service for local area residents and businesses.

Location

InterBel to install approximately 1,560 feet of fiberoptic cable across two segments of National Forest System land along Farm to Market Road within the County right of way.

Project timeline

1
Scoping Start
04/14/2021
2
Decision
04/2021 (Estimated)
3
Implementation
05/2021 (Estimated)

NEPA / regulatory detail

Categorical Exclusion32.2 (2), 36 Cfr 220.6(E)(2)
Special AuthorityNot Applicable / Other
Notice and Comment RegulationNot Subject to Regulations
Project ActivitySpecial Use Authorizations
InterBel Fiber Optic Cable InstallDecision Signed Date: 04/29/2021
ForestsFlathead National Forest
DistrictsTally Lake Ranger District
Legal Land DescriptionNW 1/4 SW 1/4 Section 36, T31N, R23W
Special use management