A project to reduce fuels, provide egress to local communities, improve diversity and resilience of vegetative communities, and contribute to the economy.
Location
Project is located on the northwest side of the Flathead Valley on the Tally Lake Ranger District.
Project timeline
1
Scoping Start
12/08/2021
2
Comment Period
06/17/2022
3
Objection Period Start
08/22/2022
4
Decision
04/2024 (Estimated)
5
Implementation
06/2024 (Estimated)
NEPA / regulatory detail
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | 218 (2013) Non-HFRA |
| Project Activity | Road Decommissioning; Fuel Treatments (Non-Activity Fuels); Forest Vegetation Improvements; Trail Management; Road Maintenance; Road Improvements/Construction; Timber Sales (Green) |
| Round Star Project | Decision Signed Date: 04/03/2024 |
| Forests | Flathead National Forest |
| Districts | Tally Lake Ranger District |
| Legal Land Description | Not Applicable |