Special Use Permit Amendment- Add approximately 350 feet of new cable to be installed along Jim Creek Road for approximately 138 feet to the intersection of Peck Lake Road and north along Peck Lake Road for approximately 216 feet to private property.
Location
Near the intersection of Jim Creek and Peck Lake road close to Condon, MT.
Project timeline
1
Scoping Start
11/29/2021
2
Decision
01/2022 (Estimated)
3
Implementation
01/2022 (Estimated)
NEPA / regulatory detail
| Categorical Exclusion | 32.2 (3), 36 Cfr 220.6(E)(3) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | Not Subject to Regulations |
| Project Activity | Special Use Authorizations |
| Missoula Electric Co-oP - Jim Creek Line | Decision Signed Date: 01/06/2022 |
| Forests | Flathead National Forest |
| Districts | Swan Lake Ranger District |
| Legal Land Description | NW � Section 32, T22N, R17W, PMM |