The project proposes to install approximately 5,700-feet of single-phase electrical underground line and 2 fiberglass junction boxes along National Forest System Roads 9780 (SEC 23, T20N, R17W) and 90240 (SEC 24, T20N, R17W).
Location
The project is located approximately 2.5 miles west of Swan Valley School, and just north of Stoner Lake, in Township 20 North, Range 17 West, Sections 23 and 24.
Project timeline
1
Scoping Start
04/10/2023
2
Decision
05/2023 (Estimated)
3
Implementation
07/2023 (Estimated)
NEPA / regulatory detail
| Categorical Exclusion | 32.2 (3), 36 Cfr 220.6(E)(3) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | Not Subject to Regulations |
| Project Activity | Electric Transmission |
| Missoula Electric Cooperative Stoner Lake Road Line Extension | Decision Signed Date: 05/11/2023 |
| Forests | Flathead National Forest |
| Districts | Swan Lake Ranger District |
| Legal Land Description | Not Applicable |