Salvage and sanitation harvest on 150 acres to removed trees effected by a wind event. Project requires 0.5 miles of temporary road. Temporary road is obliterated after project activities are completed.
Location
Big Belt Mountains
Project timeline
1
Scoping Start
11/01/2016
2
Decision
04/2017 (Estimated)
3
Implementation
05/2017 (Estimated)
NEPA / regulatory detail
| Categorical Exclusion | 32.2 (5), 36 Cfr 220.6(E)(5); 32.2 (13), 36 Cfr 220.6(E)(13); 32.2 (14), 36 Cfr 220.6(E)(14) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | Not Subject to Regulations |
| Project Activity | Timber Sales (Salvage) |
| Holloway Blowdown | Decision Signed Date: 04/28/2017 |
| Forests | Helena National Forest; Lewis And Clark National Forest |
| Districts | Townsend Ranger District |
| Legal Land Description | T7&8N, R4E |