Issue a permit for the construction of a fire station near the York subdivision. Permit allows a special use authorization on 5 acres or less of National Forest land.
Location
Helena Ranger District
Project timeline
1
Scoping Start
02/13/2018
2
Decision
08/2018 (Estimated)
3
Implementation
09/2018 (Estimated)
NEPA / regulatory detail
| Categorical Exclusion | 32.2 (3), 36 Cfr 220.6(E)(3) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | Not Subject to Regulations |
| Project Activity | Facility Improvements/Construction |
| York Substation | Decision Signed Date: 08/31/2018 |
| Forests | Lewis And Clark National Forest |
| Districts | Helena Ranger District |
| Legal Land Description | Not Applicable |