This project will Obliterate 2-3 miles of riparian jeep trail from Yogo Hill to Arch Coulee and relocate- some short sections of jeep trail from Arch Coulee west to private inholding that arc causing resource damage.
Location
T13N, R11E, Sections 31,32 and 33.
Project timeline
1
Scoping Start
04/13/2021
2
Decision
06/2021 (Estimated)
3
Implementation
07/2023 (Estimated)
NEPA / regulatory detail
| Categorical Exclusion | 32.2 (20), 36 Cfr 220.6(E)(20) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | Not Subject to Regulations |
| Project Activity | Road Decommissioning; Trail Management; Road Improvements/Construction; Watershed Improvements |
| Middle Fork Judith Riparian Road Restoration | Decision Signed Date: 06/30/2021 |
| Forests | Lewis And Clark National Forest |
| Districts | Musselshell Ranger District |
| Legal Land Description | Not Applicable |