Northwestern Energy to replace power poles, upgrade power pole equipment, relocate and add power poles along their existing powerline right-of-way between 1973 Rimini Road to the intersection of Rimini Road and Minnehaha Creek Road.
Location
Right-of-way between 1973 Rimini Rd to the intersection of Rimini Rd and Minnehaha Creek Rd.
Project timeline
1
Scoping Start
07/29/2024
2
Decision
08/2024 (Estimated)
3
Implementation
08/2024 (Estimated)
NEPA / regulatory detail
| Categorical Exclusion | 32.2 (2), 36 Cfr 220.6(E)(2) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | Not Subject to Regulations |
| Project Activity | Special Use Authorizations |
| NWE Rimini Road Pole Replacements, Relocations, Additions Decision Memo | Decision Signed Date: 08/13/2024 |
| Forests | Lewis And Clark National Forest |
| Districts | Helena Ranger District |
| Legal Land Description | T9N, R5W, S16/S17/S20/S29 |