The project would reduce fire risk by removing the existing overhead primary lines and pones and installing new underground primary conductor.
Location
Little Belt Mountains on Kings Hill near Showdown Ski Area.
Project timeline
1
Scoping Start
10/2024 (Estimated)
2
Decision
11/2024 (Estimated)
3
Implementation
03/2025 (Estimated)
NEPA / regulatory detail
| Categorical Exclusion | 32.2 (2), 36 Cfr 220.6(E)(2) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | Not Subject to Regulations |
| Project Activity | Special Use Authorizations |
| Forests | Lewis And Clark National Forest |
| Districts | White Sulphur Springs Ranger District |
| Legal Land Description | Sec 34 T13N, R8E, Sec 3, T12N, R8E |